DRAFT OVERALL SCHEDULE 5-8-2002

ARTESIA BLVD/INGLEWOOD AVE IMPROVEMENT PROJECT

START
COMPLETE
STATUS
NOTE

UTILITIES

5-13-2002
6-15-2002

CITY OF REDONDO BEACH - Design

RESURFACING

Design 90% complete

Distributed to neighboring Cities - back May 2002.

SIGNALIZATION

Rindge

Design complete - out to bid

Construction to begin end of summer 2002 (material lead time - 3 months).

Artesia

Design in process

NRBBA meeting to receive input - June 13, 2002. Design complete - summer 2002.

STREETSCAPE IMPROVEMENTS

Survey

In process - complete 3 to 4 weeks

Design

In process

  • Present opportunities & constraints - June 2002
  • Receive input form public - June 2002
  • Present conceptual alternatives - July 2002
  • Final conceptual design - Sept 2002
  • Completion of construction doc's - Nov 2002

CITY OF REDONDO BEACH - Construction

Bid all projects

Dec 2002/Jan 2003

Analyze bid

Jan/Feb 2002

Award

Feb 2002

Construction

March 2003

Contact Information: City of Redondo Beach
Maureen Lull, Project Manager (310) 372-1171 x3252
Artesia Blvd Construction Hotline (310) 318-0649